TESTIMONIAL: RESIDENTIAL SUBDIVISION
Concrete Science recently completed the foundation correction for Steven-Scott Management Company. The work entailed extensive foundation repair on the 16 slab-on-grade structures, drainage correction via sewer evacuation and soils correction in the affected areas.
The project went extremely well considering the corrections and logistics involved in maintaining building access for the residents during construction. Although the originally projected 12 week schedule crept into the 13th week due to a few rain days, the construction supervisor for the project asserted that, “the project went very smooth considering the logistics and complications involved with the invasive nature of the work.”